In the early morning of June 12th, as the last cubic meter of concrete was poured and the middle span of the continuous girder of the Shangqiu Main Canal Bridge, the largest-span continuous girder along the Lantai Expressway, was successfully closed! 

The closure of continuous Girder of Shangqiu Canal Bridge

The closure of continuous Girder of Shangqiu Canal Bridge

The closure of continuous Girder of Shangqiu Canal Bridge 

The Shangqiu Main Canal Bridge of the Lantai Expressway Package 1 is located in Lankao County, Henan Province . The total length of the bridge is 622.9 meters. The third joint of the upper structure adopts a cast-in-place prestressed concrete continuous box girder with a span of 75+135+75 meters,which is the longest continuous girder in the entire line. The bridge is a double-width structure, constructed using the Boyoun form travelers cantilever casting method.

Cantilever Construction

Bridge Cantilever Construction

It also crosses a first-class protected water source, with high environmental protection requirements and great construction difficulties. To ensure the smooth completion of the continuous girder construction, the project department carefully prepared a special construction plan, held numerous construction special meetings, and provided detailed briefings on construction preparation, material supply, equipment configuration, and safety management. At the same time, information technology was implemented, and cameras were installed at the construction site to realize 24/7 remote monitoring of the construction site and enhance process control.

Before pouring, assign special personnel to inspect the installation of formwork and steel bar binding in the closure section, reinforce on-site safety technical support, and select a time with low temperature and small temperature difference in the early morning for concrete pouring to ensure that all indicators meet the requirements and guarantee the quality of the closure of the continuous girder.

Currently, Boyoun has sufficient materials and a reasonable warehouse layout.After years of technical experience and product optimization,the universal rate of cantilever form traveler has reached more than 90%, greatly improving the efficiency of design and matching.

Boyoun Warehouse Workshop

Boyoun Warehouse Workshop

Boyoun provides standardized full-cycle services from pre-sales to in-sales and after-sales. We focus on customer needs, and continually improves service awareness and quality. We are committed to providing personnel tracking, pre-training, full technical support, rapid response, and rapid closed-loop support, continuously improving value for customers. 

Construction plan demonstration meeting

Construction Plan Demonstration Meeting

The continuous girder has been successfully closed, marking a breakthrough in the project and laying a solid foundation for the subsequent construction. Upon completion of the project, it will have a significant impact on improving the regional transportation network, improving transfer efficiency among road networks, and promoting rapid economic development along the line.

In the future, Boyoun will also continue to promote product standardization and parametrization to reduce costs for customers, increase efficiency, and achieve common progress.


Gallery
  • Main Canal Bridge Project
  • Main Canal Bridge Project
  • Main Canal Bridge Project
Products Used
Get In Touch

International Department: Room 2211-2212, Tower C of Wanda Plaza, Tongzhou District, Beijing 101118, China.

+86-13021287080

info@boyoun.cn

© Copyright 2020 Shandong Boyoun Heavy Industries Co., LTD. Design by BontopBlog